The
Process
Step
1
The ground is marked
with spray paint or a string line. A small sod cutter is used to
remove the grass around the existing beds. This will not disturb existing beds. The
ground is leveled and tamped before the curbing is
extruded.

Step 2
The concrete is mixed
onsite using a small mixer and trailer. There is no heavy equipment
or concrete trucks on your
yard..

Step
3
The concrete is
dumped into wheel barrows and taken and shoveled into the curbing
machine. It is extruded from
the curbing machine as a continuous piece of concrete
curbing.
Step
4
The curb is then
smooth finished with a hand trowel. It can also be topped with a
colored slurry mixture and
textured with our
special stamping tools if
desired.

Step
5
Control/Expansion
joints are cut every 3-4 feet while the concrete is still wet. The
cuts are approximately 40% into the
curb.  |